A new riverside fitness and recreation area expected for Huntly East is now expected to be finished four months later than its original completion date.
The delay is due to ground conditions in the area which have been driven by river levels, says Waikato District Council.
Initially expected to be finished by the end of June, Huntly river-walkers will now have to wait until the end of October, or early November, to enjoy the new developments to the area.
“The fitness module will now be installed once the water levels have dropped to the appropriate level,” said Council’s open spaces services manager, Glyn Morgan.
The gear that needs to be installed at the site includes static fitness equipment, designed to be used outdoors. Its later arrival is not the only change of plan to come from the site’s location.
“Although a natural surface material (such as hoggin) was initially preferred for its aesthetic and environmental qualities, concrete was selected due to its superior durability and ability to withstand the site conditions.”
Once completed, the area will serve as a valuable community-focused space, Morgan said.
“This improved community space is a place where whanau and friends can gather, share kai, and engage in physical activity.
“The fitness trail is designed to cater to all fitness levels and ages and provide an accessible and enjoyable environment for exercise. It will also foster social interaction within the community.”
“This work is being completed in support of community wellbeing and to encourage recreational use of the reserve and its connectivity.”
The development is being co-funded by WEL Energy Trust, and is being supported by local iwi, the Huntly Community Board, and Waikato District Councillors.